Project Name :
 DESIGN AND CONSTRUCTION OF
 COMBINED COUNTERNARCOTICS
 CONTROL FACILITY, PHASE II
 
 Project Location :
 PUCALLPA, PERU
 
 Project Links :
» Open new Project
» Close this Project
           

Base bid, bid option nº1 ( gym / casino building), bid option n°2 (north parking bay and service road) and bid option n°3 (south parking bay and service road). 1,840 m3 reinforced concrete, 6,300 m2 x .25 m sub-base, 6,300 m2 x .15 m base course, 5,100 m2 compacted concrete, 700 x .20 concrete pavement in parking areas, 600 m2 of flexural pavement, 3,400 m3 unclassified excavation, storm drainage system with concrete culverts, supply and install. 420 m 10 kv high tension line incl. poles, transformers, sub-station and 750 m secondary electrical line; hvac systems. CEGAZ performed all work and always ahead on schedule.
The project consisted in the design and construction of site installations (fences, gates, site offices, warehouse for materials and tools, machine shop, carpentry shop, welding shop, power house building, aggregates crush plant, concrete plant, storage areas, water supply systems incl. deep well - water tanks and underground storage tanks, sewer systems, electrical supply systems, dressing and sanitary installations for workers, kitchen and cafeteria), compacted concrete access roads and storm drainage system with concrete culverts, design and construction of different buildings (barracks facility, gym/casino, power house, pumping house, conference room, offices) preliminary works, earthworks, concrete and flexural pavements, concrete works: reinforced concrete in footings, beams, columns; masonry, stucco, revetments and plaster, steel structures, wood works, steel works, sanitary installations (water distribution and sewer systems), electrical installations (primary and secondary lines, power distribution system, high tension supply line incl. power station), furnishings for barracks facility, gym/casino, conference room, offices, equipment installation (supply and installation of other equipment like: deep well with an hydropneumatic water supply system, electrical grounding systems, lightning systems, telephone systems, cable/tv system, special electrical outlets 110 volts and 230 volts, HVAC systems).
 

1 Clearing and Grubbing m2 95,600
2 Non classified excavation m3 44,500
3 Subgrade shaping m2 40,200
4 Compact Concrete (e = 4") m2 35,700
5 Selected Subbase "D" m3 38,100
6 Crushed base graduation "B" m3 13,400
7 Geotextil m3 6,300
8 Flexural Concrete slab m3 1,900
9 Reinforced structural concrete m3 1,560
10 Sheet asphalt 5 cm. m2 18,600
11 Storm drainage system ml 3,100
12 Water supply well 8" ml 60
13 Pumping House with motor driven pump of 8 lts / sec and hydropneumatic system unit 1
14 Power house, including generator of 250 KVA (backup) unit 1
15 Supply and installation of high tension line 10 KV including poles and transformers (03) pad mounted type ml 2,300
16 Manholes unit 38
17 Supply and installation of sewer system (including primary and secondary system, grease traps, septic tanks, chlorination tanks, oxidation ponds) unit 1