| Project Name : |
 |
DESIGN AND CONSTRUCTION OF FORWARD OPERATING BASE, PHASE II, PUERTO MALDONADO |
 |
| |
| Project Location : |
 |
PUERTO MALDONADO AIRPORT – PERU |
 |
| |
| Project Links : |
 |
| » Open
new Project |
 |
| » Close this Project |
 |
| |
|
|
|
|
 |
Base bid, bid option nº1 (gym /
casino building), bid option n°2 (north parking bay
and service road) and bid option n°3 (south parking
bay and service road). 1,840 m3 reinforced concrete,
6,300 m2 x .25 m sub-base, 6,300 m2 x .15 m
basecourse, 5,100 m2 compacted concrete, 700 x .20
concrete pavement in parking areas, 600 m2 of
flexural pavement, 3,400 m3 unclassified excavation,
storm drainage system with concrete culverts, supply
and installation 420 m 10 kv high tension line incl.
poles, transformers, sub-station and 750 m secondary
electrical line; HVAC systems. CEGAZ is going to
perform all work and ahead of schedule.
The project consisted in the design and construction
of site installations (fences, gates, site offices,
warehouse for materials and tools, machine shop,
carpentry shop, welding shop, power house building,
aggregates crush plant, concrete plant, storage
areas, water supply systems incl. deep well - water
tanks and underground storage tanks, sewer systems,
electrical supply systems, dressing and sanitary
installations for workers, kitchen and cafeteria),
compacted concrete access roads and storm drainage
system with concrete culverts, design and
construction of different buildings (barracks
facility, gym/casino, power house, pumping house,
conference room, offices) preliminary works,
earthworks, concrete and flexural pavements,
concrete works: reinforced concrete in footings,
beams, columns; masonry, stucco, revetments and
plaster, steel structures, wood works, steel works,
sanitary installations (water distribution and sewer
systems), electrical installations (primary and
secondary lines, power distribution system, high
tension supply line incl. power station),
furnishings for barracks facility, gym/casino,
conference room, offices, equipment installation
(supply and installation of other equipment like:
deep well with an hydropneumatic water supply
system, electrical grounding systems, lightning
systems, telephone systems, cable/tv system, special
electrical outlets 110 volts and 230 volts, HVAC
systems). |
|
|
 |
|
|
|