Hangar, site work (1,500 m2 flexural
concrete, 800 m3 reinforced concrete, 18,000 m2
geotextile, 6,000 m2 x .15 m filter layer, 6,000 m2
x .25 m sub-base, 6,000 m2 x .15 base-course, 6,000
m2 compacted concrete, 3,150 m2 bituminous surface
treatment incl. survey works, 10,850 m3 unclassified
excavation, storm drainage system with concrete
culverts, supply and installation 1,350 m of 22.9 KV
high tension supply line incl. poles, pad mounted
transformer and 1,600 m secondary electrical line;
HVAC systems). Cegaz Inc. has been performing all
work and always ahead of schedule.
The project consisted of the design and construction
of site installations (fences, gates, site offices,
warehouse for materials and for tools, machine shop,
carpentry shop, welding shop, powerhouse building,
aggregates crush plant, concrete plant, storage
areas, water supply systems incl. deep well - water
tanks and underground storage tanks, sewer systems,
electrical supply systems, dressing and sanitary
installations for workers, kitchen and coffee shop),
preliminary works, earth works, pavement, concrete
works: reinforced concrete in footings, beams,
slabs, columns, rigid pavement, masonry, stucco,
revetments and plaster, steel structures, wood
works, steel works, sanitary installations,
electrical installations (high tension
supply line incl. power station) & supply and
installation of other equipments (rollup door, 2.00
ton overhead bridge crane, heavy compressor and air
compressed line, 6 motorized 4.50 ton sliding hangar
doors, hydropneumatic water supply system,
electrical grounding system, lighting system,
telephone system, against-explosion special
electrical outlets 110 volts and 230 volts, HVAC
systems); access roads, parking areas, incl. 3/8”
bituminous surface treatment, and storm drainage
system with concrete culverts.
|
|
1 |
Clearing and Grubbing |
m2 |
38,400 |
|
2 |
Non
classified excavation |
m3 |
31,600 |
|
3 |
Subgrade shaping |
m2 |
33,500 |
|
4 |
Compact Concrete (e = 4") |
m2 |
30,100 |
|
5 |
Selected Subbase "D" |
m3 |
31,700 |
|
6 |
Crushed base graduation "B" |
m3 |
9,900 |
|
7 |
Sub.drainage filter layer |
m2 |
8,500 |
|
8 |
Geotextil |
m2 |
17,000 |
|
9 |
Flexural concrete slab |
m3 |
1,800 |
|
10 |
Reinforced structural concrete |
m3 |
800 |
|
11 |
Storm
drainage system |
ml |
4,200 |
|
12 |
Pumping Net (8") |
ml |
1,200 |
|
13 |
Power
House including Generator of 250 KVA |
unit |
1 |
|
14 |
Supply
and installation of air compressed line to
250 psi, 10 lts/sec (including compressor,
main line 1”, secondary net ¾”) |
ml |
380 |
|
15 |
Supply
and installation of high tension line 22.9
KV including poles |
ml |
1,650 |
|
16 |
Manholes |
unit |
87 |
|
17 |
Supply
and installation of rigidly framed structure
(Hangar) (280 Ton) |
m2 |
2,400 |
|
18 |
Supply
and installation of electric sliding large
doors (Hangar) |
m2 |
480 |
|
19 |
Supply
and installation of sewer system (including
primary and secondary net, manholes, etc) |
unit |
2 |
|