Project Name :
 FORWARD OPERATING LOCATION,
 SUPPORT FACILITIES,
 MANTA AIR BASE
 
 
 
 Project Links :
» Project Schedule
» Open new Project
» Close this Project
           

Constructions included in the BASE BID: Bid Item 1 (150 Man Visiting Quarters, Admin/Dining Building, Site Work; approx. Building Area=4,120.00 m2), Bid Item 2 (Fire Crash/ Rescue Station, Site Work approx. Building Area=2,019.20 m2), Bid Item 3 (Aircraft Maintenance Unit, Squadron Operations, Gate House, Site Works; approx. Building Area=2,982.64 m2), Bid Item 4 (Aircraft Maintenance Hangar and Nose Dock Facility, Site Work; approx. Building Area=2,688.00 m2), Bid Item 5 (Aerospace Ground Equipment AGE Shop, Hazardous Materials HazMat Storage, LOX Storage, Site Work; approx. Building Area=1,106.16 m2), Bid Item 6 (100 Man Visiting Quarters, Site Work; approx. Building Area=2,076.60 m2); they include: Cleaning & Grabbing, Unclassified Excavation, Select Borrow Fill, Capillary Drainage Layer, Structural Foundations, Concrete Structures, Steel Structures, Steel Buildings/Components, Reinforced Concrete Blocks Masonry, Flexible Concrete Pavement, Asphalt Pavement, Mechanical Systems, Plumbing Systems ( Incl. All Sanitary Works, Piping, Hot and Cold Water Piping, Fittings, etc); Interior Installations; Supply & Installation of Food Service Areas (Incl. Dining Facilities); Supply & Installations of Electrical/Electronics Systems (Incl. All Electrical Works in High and Low Tension Aerial & Underground, Ducts & Piping, Transformers, Standby Generator Power Systems; Supply and Installation of Communication Systems; Cathodic Protection; SCIF; Fire Protection Systems, Housing Units, Maintenance Facilities, Hazmat Facilities; execution of all Finish Works.
Construction of Site Installations (Fences, Gates, Site Offices, Warehouses for Material and Tools, Machine Shops, Carpentry Shops, Welding Shops, Powerhouse Buildings, Concrete Batching Plant, Asphalt Plant, Storage Areas, Water Supply Systems incl. Water Tanks, Water Cistern Underground Storage Tanks, Sewer Systems, Electrical Supply Systems, Dressing & Sanitary Installations for Workers, Site Canteens), Access Roads, Storm Drainage Systems incl. Concrete Culverts; construction of all contract Buildings and Facilities included in the contract (150-MAN VQ1, ADM./DINING FACILITY, FIRECRASH/RESCUE STATION, AMU, SQDR. OPERAT. GATE HOUSE, A.M. HANGAR, AGE SHOP, HazMat STORAGE, LOX STORAGE, 100-MAN VQ2), including: preliminary works, earthworks, flexural concrete pavements and concrete works (reinforced
concrete foundations, columns, beams, reinforced concrete masonry walls, concrete slabs 1st & 2nd floors); stucco and plastered walls, steel structures & steel components for roofing, wood works, sanitary installations (water supply lines, water plant, hydroneumatic systems, hot & cold water installations), sewer lines & systems, electrical installations (aerial & underground electrical primary &
secondary supply lines, and electrical systems), power distribution systems incl. power stations & transformers, grounding systems, special lighting systems, special lightning systems; special fire protection systems; fuel tank installations; air compression systems; welding equipment; painting equipment; communication systems, telephone systems, cable/TV systems; HVAC systems; food service furnishings and facilities; supply & installation of other diverse equipment.
 

1 Massive excavation m3 900,000
2 Selected material backfilling m3 540,000
3 Subbasem m3 51,000
4 Granular Base m3 42,000
5 Concrete Pavement m3 76,000
6 Diverse concrete structures m3 35,000
7 Asphalt Pavement m3 49,000
8 Gabions m3 30,000
9 Concrete culverts 1.0 x 1.20 mt Ml 1,500
10 Drainage gutter Ml 6,000
11 Electric Ducts for illumination Ml 12,000
12 Communication Ducts Ml 8,000
13 Electric Ducts for High Tension Ml 10,000
14 Runway lighting system Unit 800
15 Grounding system Unit 1,200
16 Pavement joint seals Ml 160,000
17 Pavement joint sections ml 86,000
18 Horizontal signaling M2 26,000
19 Vertical signaling unit 420
20 Concrete and Asphalt Grooving M2 135,000
21 Generators 150 KVA unit 22